INVESTMENT PROGRAM
 

JSC “Quadra - Power Generation” implements a large-scale investment program of generating capacities renovation, which stipulates construction of 1092 MW of new power units for the period till 2015 within the framework of performance of obligations according to Capacity Supply Agreements (CSA) in respect of capacity supply to the electricity market. The total amount of the company’s investments into implementation of the investment program exceeds RUR 39 billion.

Now 4 projects of gas and steam energy units construction have been implemented out of 10 planned ones. These are GSU 52 MW at the Elets TPP, which has 52 MW of capacity, and at the Voronezh TPP-2, which has 115 MW of capacity; their startup was in 2009 and 2010. In 2011, construction of GTU-30 MW at the Kaluga TPP and GSU-115 MW in Kursk was completed. In 2012, start-up of GTU-30 MW at the Livny TPP in the Orel Region and GSU-190 MW at the Novomoskovsk SDPS in the Tula Region will be performed. Implementation of the gas steam units projects at the Dyagilev TPP (the Ryazan Region), Alexin TPP (the Tula Region), Voronezh TPP (the Voronezh Region) and Kursk TPP-1 (the Kursk Region) and their commissioning are planned in 2013-2015.


Investment projects of JSC “Quadra – Power Generation”


SITUATION OF GENERATION FACILITYRF ENTITY FACILITY NAMEINSTALLED CAPACITY OF
FACILITY (MW)
TIME OF COMMISSIONING
Elets TPP (branch – Eastern Generation)Lipetsk
Region
GSU522009
Voronezh TPP-2 (branch – Voronezh Regional Generation)Voronezh
Region
GSU1152010
Boiler of North -Western District of Kursk (branch – Southern Generation) Kursk
Region
GSU1152011
Kaluga TPP (branch – Central Generation)Kaluga
Region
GTU302011
Livny TPP (branch – Central Generation)Orel
Region
GTU302013
Novomoskovsk SDPS (branch – Central Generation)Tula
Region
GSU1902013
Dyagilev TPP (branch – Central Generation)Ryazan
Region
GSU1152014
Alexin TPP (branch – Central Generation)Tula
Region
GSU1152014
Voronezh TPP-1 (branch – Voronezh Regional Generation)Voronezh
Region
GSU2232015
Kursk TPP-1 (branch – Southern Generation)Kursk
Region
GSU1152016
 